[or-cvs] r21414: {projects} update progress, new gantt chartt, note we're falling behind (projects/todo)

Andrew Lewman andrew at torproject.org
Fri Jan 15 17:37:51 UTC 2010


Author: phobos
Date: 2010-01-15 17:37:50 +0000 (Fri, 15 Jan 2010)
New Revision: 21414

Modified:
   projects/todo/tpo-highlevel-tasklist.tjp
   projects/todo/tracking-gantt.pdf
Log:
update progress, new gantt chartt, note we're falling behind in a few
tasks.


Modified: projects/todo/tpo-highlevel-tasklist.tjp
===================================================================
--- projects/todo/tpo-highlevel-tasklist.tjp	2010-01-15 12:47:55 UTC (rev 21413)
+++ projects/todo/tpo-highlevel-tasklist.tjp	2010-01-15 17:37:50 UTC (rev 21414)
@@ -34,9 +34,9 @@
 task op_main "Business Operations" {
   task op_one "Community Forums" {
     start 2009-11-19
-    end 2009-12-31
+    end 2010-01-31
     allocate andrew, volunteer, vendor
-    complete 50
+    complete 75
     }
   task op_two "Website Documentation Update" {
     start 2009-11-19
@@ -52,27 +52,27 @@
   }
   task op_four "Main Website Overhaul" {
     start 2009-12-01
-    end 2010-02-28
+    end 2010-03-31
     allocate andrew, vendor
-    complete 5
+    complete 10
   }
   task op_five "Legal Directory" {
     start 2009-11-19
     end 2010-01-31
     allocate andrew, volunteer
-    complete 60
+    complete 100
   }
   task op_six "Audit Prep" {
     start 2009-11-19
-    end 2009-12-31
+    end 2010-01-31
     allocate andrew, melissa, auditor
-    complete 70
+    complete 90
   }
   task op_seven "Tor Logo Store" {
     start 2009-11-19
-    end 2009-12-31
+    end 2010-01-31
     allocate andrew, karen, vendor
-    complete 25
+    complete 50
   }
   task op_eight "2010 Budget" {
     start 2009-11-19
@@ -84,7 +84,7 @@
     start 2009-11-19
     end 2010-01-31
     allocate andrew, karen
-    complete 15
+    complete 35
   }
   task op_ten "Migrate wiki" {
     start 2009-11-19
@@ -100,31 +100,31 @@
   }
   task op_twelve "Advocacy Videos" {
     start 2009-11-19
-    end 2009-12-31
+    end 2010-01-31
     allocate karen, carolyn
-    complete 60
+    complete 90
   }
   task op_thirteen "Brochure" {
     start 2009-11-19
-    end 2009-12-21
+    end 2010-01-31
     allocate karen
     complete 50
   }
-  task op_fourteen "2009 Donation Drive" {
-    start 2009-11-19
-    end 2009-12-31
+  task op_fourteen "2010 Donation Drive" {
+    start 2010-01-01
+    end 2010-12-31
     allocate karen, andrew
-    complete 50
+    complete 10
   }
   task op_fifteen "Tor Support Organization" {
     start 2009-11-19
-    end 2010-01-31
+    effort 60d
     allocate andrew
     complete 0
   }
   task op_sixteen "Friends of Tor International" {
     start 2009-11-19
-    end 2010-02-28
+    effort 60d
     allocate andrew
     complete 0
   }
@@ -144,7 +144,7 @@
     start 2009-12-07
     end 2009-12-31
     allocate andrew, karen
-    complete 0
+    complete 100
   }
 }
 
@@ -159,7 +159,7 @@
     start 2009-11-19
     end 2009-12-31
     allocate carolyn, volunteer
-    complete 50
+    complete 75
   }
   task tr_three "Arabic Translator" {
     start 2009-11-19
@@ -171,13 +171,13 @@
     start 2009-11-19
     end 2009-12-31
     allocate carolyn, volunteer
-    complete 50
+    complete 75
   }
   task tr_five "Chinese Translator" {
     start 2009-11-19
     end 2009-12-31
     allocate carolyn, volunteer
-    complete 50
+    complete 75
   }
   task tr_six "Spanish Translator" {
     start 2009-11-19
@@ -216,13 +216,13 @@
     start 2009-11-19
     end 2009-12-31
     allocate melissa, andrew
-    complete 75
+    complete 100
   }
   task fin_four "Monthly Report Generation" {
     start 2009-11-19
     end 2009-12-31
     allocate melissa
-    complete 75
+    complete 85
   }
 }
 
@@ -272,9 +272,9 @@
   task rd_four "Performance Improvements" {
     task rd_four_one "Waterloo Performance Patch" {
       start 2009-11-20
-      end 2009-12-31
+      end 2010-02-28
       allocate roger, nick
-      complete 85
+      complete 80
     }
     task rd_four_two "Microdescriptor Proposal" {
       start 2009-12-14
@@ -306,7 +306,7 @@
     start 2009-11-19
     end 2009-12-16
     allocate steven
-    complete 10
+    complete 100
     }
     task rd_seven_two "Proposals from suggested defenses" {
       start 2009-11-19
@@ -364,36 +364,36 @@
     start 2009-11-19
     end 2009-12-21
     allocate karsten
-    complete 50
+    complete 100
   }
   task m_three "Metrics Reporting" {
     start 2009-11-19
     end 2009-12-31
     allocate karsten
-    complete 25
+    complete 100
   }
   task m_four "MaxMind GeoIP DB sync" {
     start 2009-12-07
     end 2009-12-31
     allocate karsten
-    complete 15
+    complete 25
   }
   task m_five "DirAuth to DB Direct" {
-    start 2009-12-07
-    end 2009-12-31
-    allocate karsten
+    start 2010-01-02
+    effort 14d
+    allocate karsten, volunteer
     complete 0
   }
   task m_six "Weekly Bridge Stats" {
-    start 2009-12-07
-    end 2009-12-31
-    allocate karsten
+    start 2010-01-02
+    end 2010-02-28
+    allocate karsten, roger
     complete 50
   }
   task m_seven "Weekly TorPerf Stats" {
-    start 2009-12-07
-    end 2009-12-21
-    allocate karsten
+    start 2010-01-02
+    end 2010-02-28
+    allocate karsten, roger
     complete 50
   }
 }
@@ -481,7 +481,7 @@
     start 2009-11-19
     end 2009-12-31
     allocate christian
-    complete 75
+    complete 100
   }
 }
 
@@ -506,7 +506,7 @@
   }
   task bdb_four "implement email help command" {
     start 2009-11-19
-    end 2010-01-031
+    end 2010-01-31
     allocate christian
     complete 0
   }
@@ -541,7 +541,7 @@
     start 2009-11-19
     end 2009-12-31
     allocate bruce
-    complete 25
+    complete 85
   }
 }
 

Modified: projects/todo/tracking-gantt.pdf
===================================================================
(Binary files differ)



More information about the tor-commits mailing list